  • The Nassau Guard Gate involved the construction of Earth Dams on the east and west side of the historically significant Trent-Severn Canal, and the construction of a Concrete Structure within the canal complete with Steel Sector Gates and associated electromechanical components. The Guard Gate would be used in the case of a major flooding event and would redirect water upstream to the Otonabee River, protecting the homes, businesses, and critical infrastructure adjacent to the canal. The Work also included the construction of a flow bypass system, and installation of a new watermain. The bypass system, consisting of a 1200mm diameter HIPRESCON pipe, cast-in-place Inlet and Outlet Structures, and an electrically-powered slide gate, would allow for the gates to be preventatively closed in the winter time, enabling an ecological flow to maintain familiar levels in the canal, and help protect important wetlands, fish habitat and fish spawning grounds.
  • The Scope of Work included excavation, grading, diving operations, cofferdams, dewatering, rock grouting, rock anchors, structural concrete and complex formwork, structural steel fabrication and erection, electrical works, mechanical works, watermains, bypass pipes, culverts, environmental protection measures, and landscaping

Requirements

  • Phase 1 (January – March, 2018): Clearing and Grubbing, Canal Dredging and removal of weathered rock to maintain deep navigational clearance, Cofferdam installation, and Excavation of West Bank within Cofferdam Work Area
  • Phase 2 (April – November, 2018) : Installation of Watermain across East and West Bank, Construction of Earth Dams, Construction of By-Pass Pipe and By-Pass Inlet and Outlet Structures, and Construction of the West Side of Concrete Structure for the Guard Gate.
  • Phase 3 (November 2018 – March 2019) : Cofferdam Installation, Watermain Installation Across the Canal, Construction of East Side of Concrete Structure for Guard Gate, Concrete Apron on the Canal Bed, Stop Sills, Sector Gate Embedded Parts (Gate Sill, Pintles, Vertical Sealing Path), Sector Gate Installation, Electrical Works,
  • Phase 4 (April 2019 – May 2019): Gate Commissioning, Landscaping
Construction at the Nassau Guard Gate Replacement on Trent Severn Waterway project site

Get in Touch

Tomlinson Group Head Office

100 Citigate Drive,
Ottawa, ON K2J 6K7

Media Inquiries

Rob Pierce, Senior VP, Planning & Development

rpierce@tomlinsongroup.com

24-Hour Emergency Spill Services

Tell 
Us 
About 
Your 
Project

First Name *
Last Name *
Email Address *
Phone Number *
Company *
Message *

Share

Follow us on FacebookFollow us on LinkedInFollow us on X

Work With Us

Reach Out Today

For Complex civil projects to everyday material needs, Tomlinson delivers. Get in touch today and start working with Eastern Canada’s trusted partner for environmental, infrastructure, and construction solutions.