2016 OMCIAA Airfield Pavement Works
Project Description
The project was divided into eight stages. The schedule for this project had no margin for error. The resurfacing portion was right at the primary apron area, and had to be completed at night. The second portion (resurfacing a major taxiway by removing deteriorated surface and constructing a new heavy duty asphalt taxi surface) involved long days. For the entire project we were working adjacent to a live runway. We completed the project on time and the client is thrilled with the result.
- Mill and resurface Apron 50mm
- Modify Storm Sewer System adjacent to taxiway
- Excavation Of Taxiway
- Granular B and Granular A
- Asphalt
- Line Painting
Requirements
- Resurface Primary Apron (290M X 150M) in stages
- Line Painting including symbols
- Upgrade Storm Drainage on Live Taxiway
- Upgrade Edge Lighting on Live Taxiway
- Reconstruct Taxiway (580M X 35M) in stages
- Remove concrete base
- Install New Granular ‘B’ Sub Base
- Install New Granular ‘A’ Base
- Pave Taxiway with 140mm Asphalt



Get in Touch
Tomlinson Group Head Office
100 Citigate Drive, Ottawa, ON K2J 6K7
Media Inquiries
Rob Pierce, Senior VP, Planning & Development
rpierce@tomlinsongroup.com24-Hour Emergency Spill Services
Tell Us About Your Project

Work With Us
Reach Out Today
For Complex civil projects to everyday material needs, Tomlinson delivers. Get in touch today and start working with Eastern Canada’s trusted partner for environmental, infrastructure, and construction solutions.